|
A typical method statement
for roofing sub-contract works
1. Notification of Order
The contracts director meets staff involved in the project. The
Q.A plan is introduced and other sub-contractors identified:
Responsibility for particular tasks is confirmed, where relevant
Plans, materials, procurement, co-ordination and liason
The basic parameters are established:
Programme dates, labour resources, and overall organisation
structure including names and personnel for the main contractor
and consulting engineers.
2. Overall Planning and Programme
The Contracts Manager / Draughtsman prepares a materials procurement
schedule and sets delivery dates.
Peak labour levels within permissable working hours are determined
Sub-contractor attendance confirmed
On site facilities, health and safety, welfare arrangements
are identified
The smooth successful conclusion of any project depends on the ability
to integrate T R Freeman's works service with other principle sub-contractors.
An agreed contract programme is established and subsequent amendments
reflects the best action plan at anytime during the project.
3. Procurement of Materials
Our programme details
a) Equipment
b) Builders work completion dates
c) Drawing approval dates
d) On-site delivery dates
Once drawings are approved and a contract is signed, materials will
be selected, and ordered. Deliveries are scheduled so that all first
fix materials are on-site as a priority, all-second fix and final
fix materials delivered when required.
This procedure allows complete programme flexibility. The early
ordering of materials remains a priority of the Contracts Manager.
4. Approach to the Installation of Roofing Services
A draughts person creates working drawings detailing all particular
roofing trays, trims and supports or cladding layouts.
The Architects, Main Contractors discuss these details, before sets
of working drawings are produced.
The Manager and Foreman ensure that enough time is committed to
the installation of the works as detailed in the drawings.
As standard, T R Freeman has a production/quality control monitoring
system to ensure that each operative is working to an optimum daily
level.
All works progress in accordance with an agreed contract programme
and on-site operative numbers vary with each project.
5. Site Control
The working foreman's responsibility is to monitor, control, record
and maintain satisfactory production levels in line with the managers
requirements. Daily checks ensure problems are rectified promptly.
6. Operating and Maintenance Manuals
T R Freeman will compile all necessary technical information when
an order is placed to ensure a complete and successful handover
of the operating and maintenance manuals.
|